Tasks
14/43 complete · 4 in progress · 1 need decision
Replace pool pipes (spec upgraded)
Notes: Pipework done. Drainage status to be evaluated on next site visit.
Finish: December 2025
Completed: 15 Dec 2025
Run drainage pipes in trenches
Notes: In progress — evaluating plan.
Level terrace floor ready for resin
Finish: 24 Mar 2026
Completed: 24 Mar 2026
Level pool internal walls
Completed: 4 Apr 2026
Coping stones measured and ordered
Notes: Changed from original edging tile spec. Estimated delivery ~2 weeks from 20 Feb 2026.
Finish: 28 Mar 2026
Completed: 28 Mar 2026
Fit coping stones
Finish: 29 Mar 2026
Completed: 29 Mar 2026
Cut off corner of step
Agree tile band colour with customer
Notes: Tile samples shared. Decision needed before ordering. See tile style reference: https://www.pooltile.com.au/product/cmc655-druid-grey-kit-kat-20mm/
Completed: 26 Feb 2026
Decide tile band height: 26mm or 38mm
Notes: Must not place tile band across the jet outlet face. Options: 26mm (above jets) or 38mm (below jets).
Completed: 26 Feb 2026
Order tile band tiles and epoxy adhesive (~€2,000 materials)
Notes: Installation included at no extra charge — avoids additional wall prep cost.
Completed: 4 Apr 2026
Fit tile band
Apply first coat render on garden walls
Notes: First coat complete ~24 Mar 2026. Final coat pending.
Finish: 24 Mar 2026
Paint surrounding walls
Trim tiles back or source suitable edging at wall junction
Completed: 4 Apr 2026
Build wall around pool room ventilation pipes
Prepare pool shell surface
Notes: Fibreglass preparation subcontracted to Fabian. Includes surface clean/degrease, sand and key, and crack/void repair. Cost included in pool respray quote S00973. Start date TBC.
Apply fibreglass lining (3 layers polyester resin + epoxy)
Notes: Apply three layers of polyester resin + epoxy fibreglass lining. Subcontracted to Fabian. Cost included in pool respray quote S00973. Start date TBC.
Apply EcoFinish aquaBRIGHT — French Grey (AB3-FG)
Notes: Product in stock. Apply after coping stones fitted.
Apply terrace resin aggregate finish
Notes: Resin ordered — expected delivery end of March 2026.
Paint gate
Install shower (supply and fit)
Notes: Shower cancelled — no longer required. Quote S01227-E superseded.
Finish: December 2025
Completed: 20 Dec 2025
Hot tub electrical installation — supply, fuse box and connections
Notes: Hot tub to go next to pool heater once resin is down.
Dig channel from pump room to heater enclosure
Notes: Channel dug approx 24 Mar 2026. Large enough for drainage, water and electrical duct.
Finish: 24 Mar 2026
Completed: 24 Mar 2026
Install drainage, water pipe and electrical duct in channel
Notes: Install drainage run, fresh water supply with tap, and electrical conduit duct in the dug channel.
Shorten chimney: fit 90-degree elbow, vent through side of wall housing
Supply and install pump room entrance lid
Notes: Sourcing suitable lid. Jose had none in stock. May need to check if hole size needs enlarging.
Remove cable in old flower bed area (concreted over)
Check pool house cover hole size — may need enlarging
Remove old electric garden light
Notes: Part of prep works block
Hot tub install (supplied by MVP) — position, plumb and connect
Notes: After resin is complete — approx May 5-6
Cap small drain pipes from top to bottom terrace
Finish: 27 Mar 2026
Completed: 27 Mar 2026
Reinstate ground after channel installation
Notes: Backfill and reinstate ground surface after drainage, water and electrical duct installed in channel.
Confirm start date with Fabian for fibreglass prep and lining
Notes: Fibreglass preparation and lining subcontracted to Fabian. Start date TBC. Cost included in pool respray quote S00973. Confirm schedule before pool is ready for prep.
Fit border tiles around garden area
Trim down bottom step
Finish: 12 Mar 2026
Completed: 12 Mar 2026
Remove old tiles from steps
Re-render steps in concrete
Supply and fit step tiles
Notes: Must be completed after terrace resin. Awaiting tile colour/style decision from customer.
Apply final coat render on garden walls
Notes: First coat applied ~24 Mar 2026. Final coat to follow.
Apply final coat render on garden walls
Notes: First coat applied ~24 Mar 2026. Final coat to follow.
Repair hollow spots in terrace concrete
Notes: Completed ~27 Mar 2026. Price TBC.
Finish: 27 Mar 2026
Completed: 27 Mar 2026
Apply final coat render on garden walls
Notes: First coat applied ~24 Mar 2026. Final coat to follow.
Repair hollow spots in terrace concrete
Notes: Completed ~27 Mar 2026. Price TBC.
Finish: 27 Mar 2026
Completed: 27 Mar 2026