Crusty's Pool Refurb
Overall Project Progress10%
1 phases complete 1 in progress 8 not started
2/38
Tasks Done
9
Decisions Needed
6
Materials Tracked
€22,755.2
Paid to Date

9 decisions needed

Open decisions need to be resolved before the next phase can proceed.

Project Phases

View all tasks
Groundworks & DrainageComplete

Pool pipe replacement and drainage run in trenches. Spec changed from original quote — upgraded pipes installed.

Floor LevellingIn Progress

Level the terrace floor ready for resin application.

Pool Internal Wall LevellingNot Started

Level and prepare pool internal walls before coping and tile band.

Coping StonesNot Started

Fit coping stones around pool perimeter. Changed from original edging tile spec.

Tile BandNot Started

Fit waterline tile band inside pool. Colour and height TBC.

Wall Rendering & PaintingNot Started

Render and paint surrounding walls. Run parallel with pool prep.

Pool Shell Preparation & RefibreNot Started

Prepare pool shell surface and apply new fibreglass lining (3 layers polyester resin + epoxy).

EcoFinish Pool InteriorNot Started

Apply EcoFinish aquaBRIGHT — French Grey (AB3-FG). Product in stock.

Terrace ResinNot Started

Apply resin aggregate finish to terrace floor. Resin ordered — expected end of March 2026.

Smaller & Additional JobsNot Started

Miscellaneous additional works including electrical, plumbing, shower, gate, and chimney.

Financial Summary
Total quoted (inc tax)€49,704.20
Paid to date€22,755.20
Outstanding (quoted items)€26,949.00
Items TBC (not yet priced)7 items
Full breakdown
Materials Status
EcoFinish aquaBRIGHT — French Grey (AB3-FG)in_stock
Terrace Resin Aggregateordered
Coping Stonesordered
Tile Band Mosaic Tilesto_order
Tile Band Epoxy Adhesiveto_order
30L Grey Solar Showerto_order
Full materials list

Latest Updates

View all

Project tracker set up. Here is a summary of where we are: ✅ Pool pipework complete (spec upgraded). ✅ Coping stones ordered — estimated delivery ~2 weeks. ✅ EcoFinish French Grey powder in stock. 🔄 Floor levelling in progress. ⏳ Terrace resin ordered — expected end of March 2026. Next steps: level floor, level pool walls, fit coping stones, agree tile band colour and height, then pool prep and refibre. 3D scan of current site: https://poly.cam/capture/1570EA11-E612-4CD5-9D57-508E06537788

Canary Detect — 20/02/2026